ENTSOG TYNDP 2017 - Annex A2 - Project Details

Current TYNDP : TYNDP 2017 - Annex A

Page 2 of 620

NDP and PCI Information

Schedule

Start Date

End Date

Third-Party Access Regime

Part of NDP NDP Number

Pre-Feasibility Feasibility FEED Market Test

Considered TPA Regime Considered Tariff Regime Applied for Exemption

Yes (NDP 2016-2025)

Regulated Regulated

GCA 2015/01a

No

Currently PCI

Exemption Granted

Yes (6.4)

06/2016

Not Relevant

Permitting

10/2015

CBCA Decision Market Survey

Exemption in entry direction Exemption in exit direction

No

Supply Contracts FID Construction Commissioning

0.00% 0.00%

Not Relevant (no CBCA decision)

10/2020

2020

2020

Pipelines and Compressor Stations Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

The technical load factor of the pipeline is confidential and must not be published in the TYNDP.

Austrian Side

Czech Side

800

12 12

0 0

Total

PCI Details

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project, Project concerns investment in reverse flow capacity

PCI Benefits

General Criteria Fulfilled Specific Criteria Fulfilled

Yes

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Benefits

Main Driver Others Main Driver Explanation Market Integration

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Made with