ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 139 of 620
NDP and PCI Information
Schedule
Start Date
End Date 05/2012 03/2016 12/2013 09/2018 09/2018
Third-Party Access Regime
Pre-Feasibility
Considered TPA Regime Considered Tariff Regime Applied for Exemption
No (As of today there is not NPD. The project was initially included in a former draft. Afterwards the draft was amended without including this underground storage. Nowadays NPD is under study and we dont know whether this underground storage will be included or not.)
Regulated Regulated
Feasibility
07/2012 09/2012
FEED
No
Part of NDP
Market Test Permitting
Exemption Granted
Not Relevant
06/2012
Exemption in entry direction Exemption in exit direction
Supply Contracts FID
0.00% 0.00%
03/2019 03/2023
NDP Number
Construction
03/2019
Commissioning
2023
2023
Currently PCI
No
CBCA Decision Market Survey
No
Not Relevant (no CBCA decision)
Technical Information (UGS)
Storage Facility
Pinasses
Storage Facility Type
Salt Cavern
Multiple-Cycle
Yes
It will be the first storage in the area which counts with important transport, interconnection and regas facilities. The first phase of the project (8 cavities) will achieve the mentioned capacity. However it could be increased in the future.
Working Volume (mcm)
240.00
Time Schedule
Grant Obtention Date Delay Since Last TYNDP
30/09/2018
Two years delay Permitting process
Delay Explanation
Comments about the Third-Party Access Regime The current Spanish system allows Negotiated and Regulated regimes but, for the moment, only regulated storages are granted.