West to East operation of the IP Waidhaus

TRA-F-753 Update Date

Project

Pipeline including CS

FID

Advanced

26/04/2016

Extension of the existing compressor and metering station at the interconnection point Waidhaus allowing gas flows from Germany to the Czech Republic (max. 2,000,000 Nm3/h). Interruptible capacity will be created.

Description

Regulatory Decisions and similar material conditions

Sponsors

General Information

Promoter Operator

GRTgaz Deutschland GmbH GRTgaz Deutschland GmbH

Host Country

Germany Planned

Status

Website Publication Approval Status

Approved

NDP and PCI Information

Schedule

Start Date

End Date

Third-Party Access Regime

Part of NDP NDP Number

Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning

Considered TPA Regime Considered Tariff Regime Applied for Exemption Exemption Granted

Yes (Netzentwicklungsplan Gas 2015)

Regulated Regulated

304-01

No Not Relevant

Currently PCI

No

CBCA Decision Market Survey

Exemption in entry direction Exemption in exit direction

No

0.00% 0.00%

Not Relevant (no CBCA decision)

2018

2018

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Made with