ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects

East-West Pipeline RO-HU (AGRI) PROJECTED CAPACITY INCREASES Interconnection

Capacity (GWh/d)

From Zone

To Zone

Modelled Direction Yes exit

168.00

Hub Romania

Hub Hungary

DESCRIPTION OF THE PROJECT

Not available at present, since the project is in a reassessment phase. New data are expected to be available within the next edition of the TYNDP (2015-20 2 4).

EXPECTED BENEFITS

Security of Supply, Market integration (RO, HU and HU neighbours ), Diversification of sources, Diversification of routes, N-1 National (For RO, N-1 inrcreases from 1.65 to 1.73), Power-to-gas, Biogas.

COMMENTS ABOUT THE PROJECT FINANCING Public financing

Private financing

Multilateral financing