ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects
Ellund-Egtved - Energinet.dk
58
TRA-F-015
Ellund-Egtved
FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Energinet.dk
Operator
Energinet.dk
TEN-E Project ?
Project of Common Interest
Interested by PCI ?
Not defined yet
IGAs
None
energinet.dk/EN/ANLAEG-OG- PROJEKTER/Anlaegsprojekter-gas/Ellund- Egtved/Sider/Ellund-Egtved.aspx
PrivateFinancing (50,00%)
PublicFinancing (50,00%)
Web Link
Energinet.dk (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Regulated
2011
1
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
2010 Q2
+94.00
Total Compressor Power (MW)
+20.00
Applied for Exemption ?
Not relevant
Construction
2013
Exemption granted ?
Commissioning
Expected Load Factor
Not relevant
2013/4
+0.55
% Exemption in entry direction
Last completed Phase :
0%
FID
% Exemption in exit direction
0%
Baltic Energy Market Interconnection Plan GRIP 2014–2023 Annex | 5