ENTSOG Annual Report 2016

DELIVERABLE &  COMPLETION DATE

ACTIVITY

GOAL

STATUS / COMMENTS

CONSULTATION WITH

MARKET AREA

Balancing

Management of BRS for Balancing (potential change procedures or new BRS)

Publication on 7 November 2016

Stakeholders, TSOs

Completed

Publish the updated BRS for Nomination and Matching with the Common Data Exchange Solutions

Implementation support and sharing of implementation experiences

Organize a joint ACER/ENTSOG Workshop on Balancing

Organised Workshop on 7 November 2016

Stakeholders, TSOs, NRAs and ACER

Completed

Implementation monitoring

Publish the first ENTSOG report on the implementation for Balancing to assess implementation status as of 1 October 2015. Provide stakeholders the possibility to raise and discuss the implementation, functional and operational issues as well as involve stakeholders into prioritisation and propositions of solutions Publish the second ENTSOG report on the implementation for Balancing to assess implementation status as of 1 October 2016.

Publication on 8 June 2016

TSOs and ACER

Completed

Potential functionality process for BAL

No issues were raised in 2016

Update on implementation status report

Launched questionnaire to TSOs in December 2016

TSOs and ACER

On-going

Tariffs

Support during the TAR NC comitology period

Ensure the adoption of the TAR NC

On-going in 2016, expected completion early 2017

EC, ACER, TSOs

On-going

Implementation discussion

Facilitate the efficient implementation of the TAR NC

Start Implementation Document and prepare for Implementation Workshop, both to be finished early 2017 Start process in 2016 so that ENTSOG is on time to launch ques- tionnaire and collect data before 31 Dec 2017 and prepare the report by 31 March 2018 Start process in 2016 so that ENTSOG is on time to launch ques- tionnaire and prepare the report by 31 March 2018

TSOs, NRAs, ACER, Stakeholders

On-going

Develop TAR implementation monitoring

Prepare for the drafting of Implementation Monitoring report

TSOs and ACER

On-going

Develop TAR effect monitoring

TSOs and ACER

On-going

Prepare for the drafting of Effect Monitoring report

Setting up stakeholder process for TAR FUNC

To prepare for functionality process to facilitate and resolve early identification of issues/challenges

Include the TAR NC in the J-FUNC process in Q2/2017

TSOs, NRAs, ACER, Stakeholders

On-going

18 |

ENTSOG Annual Report 2016