GRIP CEE 2017 / Main Report

4.2.3 CROATIA (HR)

Croatia has two gas supply corridors. The main supply corridor is through Slovenia (at the figure marked HR1). The second one is through Hungary (marked HR2). Both supply corridors are for domestic demand at the moment. After the Croatian LNG terminal (2018) and the Ionian-Adriatic Pipeline (2023) are built, Croatia can then become a transit country.

PL

DE

SK

CZ

AT

HU

RO

2023 HR1 HR2 2020

SI

HR

2018

BG

2023

Cross-border Entry/Exit capacity 2017 (EP_IN / XP_OUT) Cross-border Entry/Exit capacity – planned 2018-2026 (EP_IN / XP_OUT) UGS/Production Entry Capacity (S / P) – withdrawal UGS Exit Capacity (S_X) – injection Domestic Exit Capacity required for Demand (D_MAX / D_AS)

HR1 Main Supply Corridor for HR HR2 2 nd Supply Corridor for HR

Figure 4.3: CEE Region N-1: HR

44 |

Central Eastern Europe GRIP 2017