Chapter IX ‘Incremental capacity’
Scope: IPs Application date: entry into force (6 April 2017)
This Chapter has one Article dealing with the tariff principles for incremental capacity . The Amended CAM NC sets out the rest of the incremental rules.
Chapter X ‘Final and transitional provisions’
Scope: IPs and non-IPs Application date: entry into force (6 April 2017)
The TAR NC requires ACER to produce a report on the methodologies and param- eters used to determine the allowed/target revenue of TSOs . To that end, the NRAs must submit the relevant information to ACER. This Chapter also addresses the treatment of the capacity- and/or commodity tariff level for existing contracts . A contract must meet two requirements to become eligible: conclusion before the entry into force of the TAR NC, and the exclusion of any change in tariff level other than indexation. Such contracts must be sent to the NRA for information. Following the precedent of the INT NC, the TAR NC contains some specific provi- sions on ENTSOG’s implementation monitoring , such as deadlines for the TSOs’ submission of information to ENTSOG, and for ENTSOG’s reporting to ACER. In addition, the TAR NC sets out the detailed procedure for dealing with the speci- ficity of interconnectors . The last Article of the TAR NC includes three different ADs for different Chapters: \\ Chapters I, V, VII, IX and X: entry into force = 6 April 2017;
\\ Chapters VI and VIII: 1 October 2017; \\ Chapters II, III and IV: 31 May 2019.