ENTSOG Tariff NC - Implementation Document 2nd Edition

CALENDAR YEAR 2020

(FR) Art. 30: Publication of tariff information before tariff period (‘NEW tariffs’) Mar 2020

(PT) Art. 30: Publication of tariff information before tariff period (‘NEW tariffs’) Jun 2020

(DK, HU, IE, NIR, RO, SE, GB) Art. 30: Publication of tariff information before tariff period (‘NEW tariffs’) Sep 2020

(BG, CZ, DE, ES, FI, GR, HR, IT, LT, LU, NL, PL, SI, SK) Art. 30: Publication of tariff information before tariff period (‘NEW tariffs’) Dec 2020

2020

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

(ENTSOG) Art. 36(1)(a): Deadline to send information to ACER on compliance with Chapters other than Chapter VIII 31 Mar 2020 (ACER) Art. 36(5): Deadline for ACER to publish a report on application of r/p/m-s in MSs 6 Apr 2020 (= EIF + 3 years)

Annual yearly capacity auctions Early Jul 2020

\\ Jan–Dec tariff period: ‘NEW’ tariffs (Oct ’20–Dec ’20), ‘NEW’ tariffs (Jan ’21–Sep ’21) \\ Apr–Mar tariff period: ‘NEW’ tariffs (Oct ’20–Mar ’21), ‘NEW’ tariffs (Apr ’21–Sep ’21) \\ Jul–Jun tariff period: ‘NEW’ tariffs (Oct ’20–Jun ’21), ‘NEW’ tariffs (Jul ’21–Sep ’21) \\ Oct–Sep tariff period: ‘NEW’ tariffs (Oct ’20–Sep ’21) \\ BE: ‘NEW’ tariffs (Oct ’20–Sep ’21) \\ AT: ‘old’ tariffs (Oct ’20–Dec ’20), ‘NEW’ tariffs (Jan ’21–Sep ’21) \\ SK: ‘old’ tariffs (Oct ’20–Sep ’21) Art. 29: Publication of tariff information before annual yearly capacity auctions Jun 2020

Figure 49: General timeline for 2020

Blue box: The deadline for ACER to publish a report on application of RPMs in MSs is calculated as three years as from the TAR NC’s entry into force, indicated by the blue box as 6 April 2020. Grey boxes: Similar to the grey boxes on the previous three timelines ‘Calendar year 2017, 2018 and 2019’, the four grey boxes on this timeline represent the deadlines for publication of the set of tariff information before the tariff period. In this year, for almost all the tariff periods, these are the ‘new’ tariffs following the ‘new’ RPM. The only exception is Slovakia which is not shown in any of the grey boxes – since the first time for publishing information before the new tariff period will only occur in December 2021. The same rule for pub- lication of tariff information on ENTSOG’s TP applies. Note that in Austria the information per Article 30 will be published in December 2020 for the new four-year tariff period starting on 1 January 2021. Red box: This box represents the date of the annual yearly capacity auctions per CAM NC.

Yellow box: Similar to the previous two timelines ‘Cal- endar year 2018 and 2019’, the yellow box represents the obligation to publish the set of tariff information be- fore the annual yearly capacity auctions, on TSO/NRA website (Article 29 of the TAR NC). The same rule on reserve prices derived following the ‘old’ or ‘new’ RPM applies (in 2020, only in Austria and in Slovakia these will be not fully ‘new’ tariffs published before the annu- al yearly capacity auctions). The same rule applies for publishing tariff information on ENTSOG’s TP. Green box: This box is linked to the green box on the timeline ‘Calendar year 2018’, and indicates ENTSOG’s report to ACER on TSOs’ compliance with the TAR NC Chapters other than Chapter VIII ‘Publication require- ments’.

170 |