ENTSOG Tariff NC - Implementation Document 2nd Edition
CALENDAR YEAR 2019
(NRAs) Art. 27(4)–(5): Deadline to decide on the results of the final consultation, calculate and publish tariffs; send the decision to ACER and the EC 31 May 2019
(NRA) Art. 28(1): Deadline to decide on the results of the consultation on M, SF, int. Di, LNG Di, ‘isolation’ Di 31 May 2019
(FR) Art. 30: Publication of tariff information before tariff period (‘old tariffs’) Mar 2019
(PT) Art. 30: Publication of tariff information before tariff period (‘NEW tariffs’) Jun 2019
(DK, HU, NIR, RO, SE, GB) Art. 30: Publication of tariff information before tariff period (‘NEW tariffs’) Sep 2019
(BE, BG, CZ, DE, ES, FI, GR, HR, IT, LT, LU, NL, PL, SI) ) Art. 30: Publication of tariff information before tariff period (‘NEW tariffs’) Dec 2019
2019
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Art. 38: APPLICATION DATE 3 31 May 2019
Annual yearly capacity auctions Jul 2019
(ACER) Art. 34(1): Deadline for ACER to publish a report on a allowed/target revenue methodologies 6 Apr 2019
(TSOs) Art. 36(2)(b): Deadline to send information to ENTSOG on compliance with Chapters other than Chapter VIII 31 Mar 2019
\\ Jan–Dec tariff period: ‘old’ tariffs (Oct ’19–Dec ’19), ‘NEW’ tariffs (Jan ’20–Sep ’20) \\ Apr–Mar tariff period: ‘old’ tariffs (Oct’ 19–Mar ’20), ‘NEW’ tariffs (Apr ’20–Sep ’20) \\ Jul–Jun tariff period: ‘NEW’ tariffs (Oct ’19–Jun ’20), ‘NEW’ tariffs (Jul ’20–Sep ’20) \\ Oct–Sep tariff period: ‘NEW’ tariffs (Oct ’19–Sep ’20) \\ BE: ‘old’ tariffs (Oct ’19–Dec ’19), ‘NEW’ tariffs (Jan’20–Sep ’20) \\ AT, SK: ‘old’ tariffs (Oct ’19–Sep ’20) Art. 29: Publication of tariff information before annual yearly capacity auctions Jun 2019
Figure 48: General timeline for 2019
168 |
TAR NC Implementation Document – Second Edition September 2017