The consultation document for the final consultation must include information listed in Table 12. The section below describes the difference between the ‘final’ and the ‘intermediate’ consultations.

CONTENT OF THE FINAL CONSULTATION DOCUMENT UNDER ARTICLE 26(1)

Article 26 (1)

Content of consultation

Comparison with Articles 29 and 30

Assumptions and justification for parameters used in the proposed RPM per Article 30(1)(a)

Article 30(1)(a): examples are provided, ‘justification’ is not covered

(a) Proposed RPM

Proposed adjustments for points with storage, LNG facilities and infrastructure ending isolation of a MS per Article 9

Article 30(1)(c)(iii): part of the ‘reference prices and other prices applicable at points other than where the CAM NC applies’ Article 29: reserve prices at points where the CAM NC applies Article 30(1)(c)(iii): part of ‘reference prices at points other than where the CAM NC applies’

Indicative reference prices

Results, components and their details for CAA per Article 5

Article 30(1)(v)(3): partially covered by ‘intra-system/cross-system split’

Assessment of the RPM

Not covered

Comparison of RPM to the CWD in Article 8

Not covered

Indicative allowed and / or target revenue

Article 30(1)(b)(i): allowed and/or target revenue

(b) Revenue and splits

Indicative transmission services revenue

Article 30(1)(b)(iv): transmission services revenue

Indicative splits of capacity-commodity revenues, entry-exit revenues, intra-system/cross-system revenues

Article 30(1)(b)(v): splits of capacity-commodity revenues, entry-exit revenues, intra-system / cross-system revenues Article 30(1)(c): covered by ‘relevant information related to their [tariffs] derivation’ Article 30(1)(b)(v)(1): covered by ‘capacity-commodi- ty split’ for commodity-based transmission tariffs Article 30(1)(b)(i) and (iv): covered by ‘allowed and / or target revenue’ and ‘ transmission services rev- enue’ for non-transmission tariffs

Manner in which they are set

(c) Commodity- based and

non-transmis- sion tariffs

Share of the allowed or target revenue to be recovered by these tariffs

For non-transmission tariffs, manner of revenue reconciliation

Not covered

Indicative tariffs

Article 30(1)(c)(i): commodity-based transmission tariffs Article 30(1)(c)(ii): non-transmission tariffs

Changes in tariffs for comparable services from the prevailing tariff period to the tariff period for which information is published – indicative comparison between: (1) prevailing tariffs at the time when the consultation document is published; and (2) indicative tariffs based on the proposed RPM Changes in tariffs for comparable services from the tar- iff period for which information in published to each subsequent tariff period until the end of the prevailing regulatory period – indicative forecast based on the proposed RPM

Article 30(2)(a)(i)

(d) Changes in

transmission tariffs

Article 30(2)(a)(ii)

At least a simplified tariff model to calculate tariffs and estimate a possible future evolution

Article 30(2)(b)

Proposed index

Not covered

(e) Fixed

payable price approach

Risk premium: calculation and proposed use

Not covered

Where and when such approach is proposed

Not covered

Process for offering capacity at IPs where both fixed and floating price approaches are offered

Not covered

Table 12: Content of the final consultation document under Article 26(1)