Specific Criteria Fulfilled Comments

Time Schedule

Grant Obtention Date Delay Since Last TYNDP

2 years

Absence of market interest and change in the scope of the project: inclusion of the looping of Midi pipeline in order to increase France to Spain capacity

Delay Explanation

Expected Gas Sourcing

Algeria, Norway, Russia, LNG ()

Benefits

Main Driver Others Main Driver Explanation The Iberian-French Corridor aims to further interconnect the Iberian peninsula with the rest of Europe. Benefit Description

Results of previous CBA (TYNDP 2015) will have to be updated on the basis of TYNDP 2017 new set of assumptions.

Barriers

Barrier Type

Description

Market

Lack of market support