Iberian-French corridor: Eastern Axis-Midcat Project
TRA-N-256 Update Date
Project
Pipeline including CS
Non-FID
Non-Advanced
20/05/2016
GRTgaz and TIGF contribution to increase the firm capacity at the VIP Pireneos through the creation of an Eastern axis. The project covers both: - the specific TIGF investment related to the creation of a new physical interconnection - new infrastructure in the core of GRTgaz network necessary to offer capacity on a firm basis It contributes to the Priority corridor "North-South gas interconnections in Western Europe"
Description
Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point
Operator
Year 2024
From Gas System To Gas System Capacity
160.0 GWh/d
TIGF
FRt
ES
Comment: Commissioning year based on a FID in 2016 and standard feasability study lead time IRU WKH $UWqUH GX 0LGL ORRSLQJ TIGF 2024 ES FRt Comment: Commissioning year based on a FID in 2016 and standard feasability study lead time IRU WKH $UWqUH GX 0LGL ORRSLQJ
VIP PIRINEOS
230.0 GWh/d
Sponsors GRTgaz section - Specific developments GRTgaz TIGF section - Specific developments TIGF
General Information
Promoter Operator
GRTgaz and TIGF
100%
GRTgaz France Planned
Host Country
Status
100%
Website
Project's URL
Publication Approval Status
Approved
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM