ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 196 of 620
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Part of NDP NDP Number
Pre-Feasibility Feasibility
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Yes (2015 TIGF NDP)
Regulated Regulated
No number
01/2016 01/2016
01/2017 06/2019
FEED
No No
Currently PCI
Market Test Permitting
Exemption Granted
Yes (5.5)
02/2019
12/2020
CBCA Decision Market Survey
Exemption in entry direction Exemption in exit direction
Supply Contracts FID
No
0.00% 0.00%
Not Relevant (no CBCA decision)
04/2019 10/2022
Construction
12/2020
Commissioning
2022
2022
Pipelines and Compressor Stations Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Pipeline Spanish Border-Barbaira + CS Barbaira
French side
900
120 120
Total
PCI Details
PCI Benefits
Project concerns investment in reverse flow capacity
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Market Integration, Security of Supply
Specific Criteria Fulfilled Comments
Time Schedule
Grant Obtention Date Delay Since Last TYNDP Delay Explanation
06/04/2016
Expected Gas Sourcing
Algeria, LNG ()
Benefits
Main Driver
Regulation SoS
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM