Fos Cavaou LNG Terminal Expansion
LNG-N-227 Update Date Description
Project
LNG Terminal
Non-FID
Non-Advanced
24/05/2016
The project aims to expand the LNG terminal capacity from 8.25 bcm/y up to 16.5 bcm/y, with possible intermediate steps
Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point
Operator
Year 2020
From Gas System To Gas System Capacity
110.0 GWh/d
Fosmax LNG
LNG_Tk_FRs
FRs
Comment: intermediate phase at 11 bcm/y (i.e. +2,75 bcm/y)
Fos (Tonkin/Cavaou)
220.0 GWh/d
Fosmax LNG
2022
LNG_Tk_FRs
FRs
Comment: corresponds to 16.5 bcm:y (i.e. + 8,25 bcm/y)
Sponsors Fosmax LNG
General Information
100%
Promoter Operator
Fosmax LNG Fosmax LNG
Host Country
France
Status
Planned