ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 189 of 620
Montoir LNG Terminal Expansion
LNG-N-225 Update Date
Project
LNG Terminal
Non-FID
Non-Advanced
12/05/2016
Description
The project aims to expand the Montoir de Bretagne LNG terminal capacity by 2.5 bcm/y, from 10 bcm/y to 12.5 bcm/y.
Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point
Operator
Year 2020
From Gas System To Gas System Capacity
100.0 GWh/d
Elengy
LNG_Tk_FRn
FRn
Montoir de Bretagne
Comment: commissioning year for storage 2022
Sponsors Elengy
General Information
100%
Promoter Operator
Elengy Elengy France
Host Country
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM