ENTSOG TYNDP 2017 - Annex A2 - Project Details

Current TYNDP : TYNDP 2017 - Annex A

Page 189 of 620

Montoir LNG Terminal Expansion

LNG-N-225 Update Date

Project

LNG Terminal

Non-FID

Non-Advanced

12/05/2016

Description

The project aims to expand the Montoir de Bretagne LNG terminal capacity by 2.5 bcm/y, from 10 bcm/y to 12.5 bcm/y.

Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Point

Operator

Year 2020

From Gas System To Gas System Capacity

100.0 GWh/d

Elengy

LNG_Tk_FRn

FRn

Montoir de Bretagne

Comment: commissioning year for storage 2022

Sponsors Elengy

General Information

100%

Promoter Operator

Elengy Elengy France

Host Country

Status

Planned

Website

Project's URL

Publication Approval Status

Approved