ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 187 of 620
NDP and PCI Information
Schedule
Start Date
End Date 06/2013 06/2017
Third-Party Access Regime
Part of NDP NDP Number
Pre-Feasibility
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Yes (GRTgaz PDD 2015)
Regulated Regulated
Feasibility
na
07/2013
FEED Market Test Permitting Supply Contracts FID Construction Commissioning
No
Currently PCI
Exemption Granted
Yes (5.6)
Not Relevant
CBCA Decision Market Survey
Exemption in entry direction Exemption in exit direction
No
0.00% 0.00%
Not Relevant (no CBCA decision)
2022
2022
Pipelines and Compressor Stations Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
$UWqUH GX 1RUG (VW
Total or partial looping
1,050
87
0
New compression station to be created depending on the amount of capacity to be created (total additional compression power for the 3 stations is equal to 41 MW) Additional power depending on the amount of capacity to be created (total additional compression power for the 3 stations is equal to 41 MW)
Cheppy CS
Dierrey CS
Morelmaison CS
Adaptation of station functionality
0
Obergailbach interconnection station
Enabling reverse flow
Additional power depending on the amount of capacity to be created (total additional compression power for the 3 stations is equal to 41 MW) Total
Voisines CS
87
0
PCI Details
PCI Benefits
Project concerns investment in reverse flow capacity
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Competition, Market Integration, Security of Supply, Sustainability
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM