ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 177 of 620
Balticconnector Finnish part
TRA-N-928 Update Date
Project
Pipeline including CS
Non-FID Advanced
24/05/2016
New bidirectional offshore pipeline (Inkoo-Paldiski, DN500, 80 bar) of 80 km, plus 50 km onshore pipeline in EE (Kiili-Paldiski pipeline, DN 700, 55 bar) and 20 km onshore pipeline in FI (Siuntio-Inkoo pipeline, DN500, 80 bar) including metering and compressor stations at both ends with a daily nominal capacity of 7.2 mcm/day. The power of each compressor station is about 10 MW. The Regulators of Finland (Energiavirasto ) and Estonia (Konkurentsiamet) have made a common CBCA decision for the Balticconnector and Estonia- Latvia interconnection project.
Description
Regulatory Decisions and similar material conditions
Capacity Increments Variant For Modelling Point
Operator
Year 2019 2019 2019 2019
From Gas System To Gas System Capacity
79.0 GWh/d 79.0 GWh/d 79.0 GWh/d 79.0 GWh/d
Baltic Connector Oy Baltic Connector Oy Baltic Connector Oy Baltic Connector Oy
FI
FI/BAC
Balticconnector / Siuntio (FI)
FI/BAC
FI
EE
FI/BAC
Balticonnector / Paldiski (EE)
FI/BAC
EE
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM