ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 175 of 620
NDP and PCI Information
Schedule
Start Date
End Date 01/2017 06/2017 06/2018 06/2017 01/2019 01/2019 01/2019 01/2020
Third-Party Access Regime
Pre-Feasibility
Considered TPA Regime Considered Tariff Regime Applied for Exemption
No (The last approved Spanish NDP ended in 2016. The Royal Decree-Law 13/2012 cancel the process of obtaining administrative authorization to transport pipelines and metering regulation stations even if they were included in this NDP.This Project was included in the NDP 2008- 2016.)
Regulated Regulated
Feasibility
01/2017 06/2017
FEED
No
Part of NDP
Market Test Permitting
Exemption Granted
Not Relevant
06/2017
Exemption in entry direction Exemption in exit direction
Supply Contracts
0.00% 0.00%
FID
NDP Number
N/A
Construction
01/2019
Commissioning
2020
2020
Currently PCI
No
CBCA Decision Market Survey
No
Not Relevant (no CBCA decision)
Pipelines and Compressor Stations Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
It is necessary the increase of the compressor station of Zamora. This infrastructure should be associated to the third Interconnection point with Portugal
Guitiriz Zamora
762
320
16,840
Total
320
16,840
PCI Details
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project, Project concerns investment in reverse flow capacity
PCI Benefits
General Criteria Fulfilled Specific Criteria Fulfilled
Yes
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Expected Gas Sourcing
Algeria, LNG (WO)
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM