Mugardos LNG Terminal: Storage Extension

LNG-N-297 Update Date Description

Project

LNG Terminal

Non-FID

Non-Advanced

06/05/2016

Construction of an additional storage tank with capacity of one hundred ninety thousand cubic meters of LNG.

Regulatory Decisions and similar material conditions

N/A

Capacity Increments Variant For Modelling Point

Operator

Year 2022

From Gas System To Gas System Capacity

Mugardos

0.0 GWh/d

Reganosa (LSO)

LNG_Tk_ES

ES

Sponsors Reganosa

General Information

100%

Promoter Operator

Reganosa Reganosa

Host Country

Spain

Status

Planned

Website Publication Approval Status

Approved

NDP and PCI Information

Schedule

Start Date

End Date 01/2015 02/2015 09/2019 09/2019 03/2020 06/2019 06/2019 12/2022

Third-Party Access Regime

Pre-Feasibility

Considered TPA Regime Considered Tariff Regime Applied for Exemption

No (The last aproved Spanish NDP ended in 2016. The Royal Decree-Law 13/2012 cancel any award procedures of new regasification plants in Spain.)

Regulated Regulated

Feasibility

01/2015 04/2019

Part of NDP

FEED

No

Market Test Permitting

Exemption Granted

Not Relevant

NDP Number

08/2019

Exemption in entry direction Exemption in exit direction

Supply Contracts

0.00% 0.00%

Currently PCI

No

FID

Construction

07/2020

CBCA Decision Market Survey

No

Commissioning

2022

2022

Not Relevant (no CBCA decision)

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM