7HQHULIH /1* 6WRUDJH 7DQN
LNG-N-184 Update Date
Project
LNG Terminal
Non-FID
Non-Advanced
19/05/2016
This project consists in a second LNG tank (150.000 m3 GNL) in Tenerife LNG Regasification Plant, resulting in a total storage capacity of 300.000 m3 (GNL).
Description
Regulatory Decisions and similar material conditions
Sponsors Gascan
General Information
100%
Promoter Operator
Gascan Gascan
Host Country
Spain
Status
Planned
Website Publication Approval Status
Approved
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Regulated Regulated Part of NDP m3 GNL) NDP Number No code in the NDP No No Exemption Granted Currently PCI No Exemption in entry direction Exemption in exit direction 0.00% 0.00% CBCA Decision Market Survey No Not Relevant (no CBCA decision) Technical Information (LNG) LNG Facility Tenerife LNG Terminal Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM