ENTSOG TYNDP 2017 - Annex A2 - Project Details

Current TYNDP : TYNDP 2017 - Annex A

Page 142 of 620

NDP and PCI Information

Schedule

Start Date

End Date 01/2009 01/2009 12/2016 03/2017 12/2019

Third-Party Access Regime

Pre-Feasibility

Considered TPA Regime Considered Tariff Regime Applied for Exemption

Regulated Regulated

Part of NDP

Feasibility

01/2009 01/2016

NDP Number

No code in the NDP

FEED

No No

Market Test Permitting

Exemption Granted

Currently PCI

Yes (5.5)

07/2016

Exemption in entry direction Exemption in exit direction

Supply Contracts FID

0.00% 0.00%

CBCA Decision Market Survey

No

07/2017 12/2021

Not Relevant (no CBCA decision)

Construction

04/2020

Commissioning

2021

2021

Pipelines and Compressor Stations Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

CS Martorell

Date of Comissioning: December 2021 Date of Comissioning: December 2021 Date of Comissioning: December 2021

36

Hostalrich - Figueras

900 900

79 28

Pipeline Figueras - French Border

Total

107

36

PCI Details

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation prior to the commissioning of the project, Project concerns investment in reverse flow capacity

PCI Benefits

General Criteria Fulfilled Specific Criteria Fulfilled

Yes

Competition, Market Integration, Security of Supply, Sustainability

This project was not simulated in PS-CBA of TYNDP 2015. Nevertheless, its benefits are expected to be similar to the ones of Full MidCat. ENTSOG PS-CBA demonstrated visible benefits for this project: ‡ A better market integration of the Iberian Peninsula will be traduced by a price convergence between Spain and France ‡ Regarding competition, this project will improve the possibility to take benefit from a cheaper LNG price or Algerian gas. ‡ At EU level, it can be considered as a way to reduce the dependency from RU gas and therefore to improve the overall security of supply. ‡ This project improves the CO2 emissions in several cases by making the gas cheaper than coal and replacing coal in specific zones.

Specific Criteria Fulfilled Comments

Time Schedule

Grant Obtention Date

19/01/2016

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM