ENTSOG TYNDP 2017 - Annex A2 - Project Details

Current TYNDP : TYNDP 2017 - Annex A

Page 12 of 620

Zeebrugge LNG Terminal - 5th Tank & 2nd Jetty

LNG-F-229 Update Date

Project

LNG Terminal

FID

Advanced

13/06/2016

Construction of a second jetty for berthing of LNG ships with a capacity from approximately 3500 mࢗ LNG up to 217000 mࢗ LNG (FID, commissioning foreseen 2016). Construction of an additional storage tank with a capacity of 180000 mࢗ LNG (FID, commissioning foreseen 2019). Potential construction of additional send-out capacity of 450000 mࢗ n)/h (non-FID).

Description

Regulatory Decisions and similar material conditions Capacity Increments Variant For Modelling Variant : FID

FID

Point

Operator Fluxys LNG

Year 2019

From Gas System To Gas System Capacity

Zeebrugge LNG

0.0 GWh/d

LNG_Tk_BEh

IB-BEhz

Capacity Increments Variant(s) For Information Only Variant : non-FID

non-FID Operator

Point

Year 2019 2019

From Gas System To Gas System Capacity

122.0 GWh/d 122.0 GWh/d

Fluxys Belgium

LNG_Tk_BEh LNG_Tk_BEh

IB-BEhz IB-BEhz

Zeebrugge LNG

Fluxys LNG

Sponsors Fluxys LNG

General Information

100%

Promoter Operator

Fluxys LNG Fluxys LNG

Host Country

Belgium Planned

Status

Website Publication Approval Status

Approved

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM