ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 119 of 620
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Pre-Feasibility Feasibility
Considered TPA Regime Considered Tariff Regime Applied for Exemption
No (This is an upstream project from the North Sea (Norway) to a Danish North Sea Platform. The project is vital for the Baltic- Pipe project (gas pipeline between Denmark and Poland). The project will be included in future national plans in connection when possibly including the Baltic Pipe.)
Not Applicable Not Applicable Not Relevant Not Relevant
09/2015
12/2016
FEED Market Test Permitting Supply Contracts FID Construction Commissioning
Part of NDP
Exemption Granted
Exemption in entry direction Exemption in exit direction
0.00% 0.00%
NDP Number
2022
2022
Currently PCI
No
CBCA Decision Market Survey
No
Not Relevant (no CBCA decision)
PCI Details
PCI Benefits General Criteria Fulfilled Specific Criteria Fulfilled
No
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Benefits
Main Driver
Market Demand
Main Driver Explanation Benefit Description
Barriers
Barrier Type
Description
Currently negotiations are ongoing with Norwegian partner. An important issue is the coordination with the Baltic pipe project (connection between DK and PL).