ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 115 of 620
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Yes (Draft Netzentwicklungsplan Gas 2016)
Regulated Regulated
Part of NDP
NDP Number
300-02
Not Relevant Not Relevant
Exemption Granted
Currently PCI
No
Exemption in entry direction Exemption in exit direction
0.00% 0.00%
CBCA Decision Market Survey
No
Not Relevant (no CBCA decision)
2020
2020
Benefits
Main Driver
Others
Main Driver Explanation Benefit Description
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM