ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 105 of 620
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Pre-Feasibility Feasibility FEED Market Test Permitting
Considered TPA Regime Considered Tariff Regime Applied for Exemption
No (Project idea. The inclusion in the NDP is planned at a later time.)
Regulated Regulated
Part of NDP
NDP Number
01/2018
No
Exemption Granted
Not Relevant
Currently PCI
No
01/2018
Exemption in entry direction Exemption in exit direction
Supply Contracts FID Construction Commissioning
0.00% 0.00%
CBCA Decision Market Survey
No
Not Relevant (no CBCA decision)
2023
2023
Expected Gas Sourcing
Russia
Benefits
Main Driver
Market Demand
Main Driver Explanation Benefit Description
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Made with FlippingBook