EUGAL - Europaeische Gasanbindungsleitung (European Gaslink)
TRA-N-763 Update Date
Project
Pipeline including CS
Non-FID Advanced
24/05/2016
It connects NOS2 with PL, NL, CZ, GP and NCG and increases the security of supply based on the market survey MORE CAPACITY (www.more- capacity.eu/en) on basis of the unit investment costs according to ACER and when not available internal cost estimations - these are preliminary costs representing the current cost esimations (04/2016) -(http://www.acer.europa.eu/official_documents/acts_of_the_agency/publication/uic%20report%20-%20gas %20infrastructure.pdf).
Description
Regulatory Decisions and similar material conditions
Capacity Increments Variant For Modelling Point
Operator
Year 2019
From Gas System To Gas System Capacity
661.2 GWh/d
GASCADE Gastransport GmbH
DEg
CZ
Comment: Level 1 - Exit Deutschneudorf2
535.2 GWh/d
GASCADE Gastransport GmbH
2020
DEg
CZ
HSK-EUGAL (CZ) / Deutschneudorf 2 (DE)
Comment: Level 2 includes Level 1 in total 1,196.4 GWh/d - Exit Deutschneudorf2
214.8 GWh/d
GASCADE Gastransport GmbH
2021
DEg
CZ
Comment: Level 3 includes Level 1+2 in total 1,411.2 GWh/d - Exit Deutschneudorf2
138.6 GWh/d
GASCADE Gastransport GmbH
2019
DEg
PL/YAM
Comment: Level 1 - Exit Mallnow
112.1 GWh/d
GASCADE Gastransport GmbH
2020
DEg
PL/YAM
Mallnow
Comment: Level 2 includes Level 1 in total 250.7 GWh/d - Exit Mallnow
85.8 GWh/d
GASCADE Gastransport GmbH
2021
DEg
PL/YAM
Comment: Level 3 includes Level 1+2 in total 336.5 GWh/d - Exit Mallnow
946.8 GWh/d
GASCADE Gastransport GmbH
2019
RU/NO2
DEg
Comment: Level 1 - Entry Vierow
612.0 GWh/d
GASCADE Gastransport GmbH
2020
RU/NO2
DEg
Vierow
Comment: Level 2 includes Level 1 in total 1,558.8 GWh/d - Entry Vierow
343.1 GWh/d
GASCADE Gastransport GmbH
2021
RU/NO2
DEg
Comment: Level 3 includes Level 1+2 in total 1,901.9 GWh/d - Entry Vierow
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM