CS Rothenstadt
TRA-F-337 Update Date
Project
Pipeline including CS
FID
Advanced
26/04/2016
New compressor station at existing site on the MEGAL system. Part of measures that increase possible gas flows from Open Grid Europe to bayernets and allow gas flows from and to storages 7fields and Haidach in Austria.
Description
Regulatory Decisions and similar material conditions
Sponsors GRTgaz Deutschland GmbH
General Information
55%
Promoter Operator
GRTgaz Deutschland GmbH GRTgaz Deutschland GmbH
Open Grid Europe GmbH
44%
Host Country
Germany Planned
Status
Website
Project's URL
Publication Approval Status
Approved
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Part of NDP NDP Number
Pre-Feasibility Feasibility FEED Market Test Permitting Supply Contracts FID Construction Commissioning
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Yes (Netzentwicklungsplan Gas 2015)
Regulated Regulated
026-06
Not Relevant Not Relevant
Currently PCI
Exemption Granted
No
CBCA Decision Market Survey
Exemption in entry direction Exemption in exit direction
No
0.00% 0.00%
Not Relevant (no CBCA decision)
2018
2018