ENTSOG TYNDP 2017 - Annex A2 - Project Details
Current TYNDP : TYNDP 2017 - Annex A
Page 77 of 620
Sponsors GASCADE Gastransport GmbH
General Information
100%
GASCADE Gastransport GmbH GASCADE Gastransport GmbH
Promoter
Operator
Host Country
Germany Planned
Status
Website Publication Approval Status
Approved
Enabled Projects
Project Code Project Name TRA-F-768 Extension Receiving Terminal Greifswald
NDP and PCI Information
Schedule
Start Date
End Date
Third-Party Access Regime
Part of NDP NDP Number
Pre-Feasibility Feasibility FEED Market Test Permitting
Considered TPA Regime Considered Tariff Regime Applied for Exemption
Yes (NOWAL)
Regulated Regulated
083-07, 409-01, ...
No
Currently PCI
Exemption Granted
No
Not Relevant
01/2016
08/2016
CBCA Decision Market Survey
Exemption in entry direction Exemption in exit direction
Supply Contracts FID
No
0.00% 0.00%
Not Relevant (no CBCA decision)
03/2016 01/2018
Construction
01/2017
Commissioning
2017
2025
Pipelines and Compressor Stations Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Rehden-Drohne
1,000
26 26
16 16
Total
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM