ENTSOG TYNDP 2015 - Annex F – Methodology

5 Monetization

The monetary analysis is based on the calculation of costs for Europe measuring the completion of the Specific Criteria defined by Regulation.

The following table defines the cost items to be calculated per country as part of the TYNDP for each Infrastructure (Low, High and PCI), Global Context and Gas Demand Scenario on the year 2015, 2020, 2025, 2030 and 2035:

COST ITEMS MONETIZED AS PART OF THE TYNDP-STEP

COST ITEM

CLIMATIC CASE

WITHOUT SUPPLY STRESS

WITH SUPPLY STRESS

Whole Year*

×

GAS SUPPLY

Whole Year*

×

COAL FOR POWER GENERATION

CO ² EMISSION FROM POWER GENERATION*

Whole Year*

×

* as the temporal optimization of the succession of one Average Summer Day, one Average Winter Day, 1-day Design Case and 14-day Uniform Risk

Table 5.1: Cost items monetized as part of the TYNDP-Step

In TYNDP, results of the monetization illustrate the potential evolution of the gas, coal and CO ² bill from one scenario to the others. They should not be interpreted as any form of forecast.

Ten Year Network Development Plan 2015 Annex F | 27

Made with