ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
PROJECTED CAPACITY INCREASES Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit
Alexandropolis LNG
187.50
LNG Terminals Greece
Hub Greece
DESCRIPTION OF THE PROJECT
The project comprises an offshore floating LNG terminal (FSRU) including mooring, flex risers, PLEM, etc. located permanently in the Sea of Thrace, NE Greece.
EXPECTED BENEFITS
Security of Supply, Market integration (SEE+Serbia+FYROM), Diversification of sources, Diversification of routes, N-1 National (Greece), N-1 Regional (SEE+Serbia+FYROM), Back-up for renewables, Power-to-gas.
COMMENTS ABOUT THE PROJECT FINANCING Public financing
Private financing
Multilateral financing
Southern Corridor GRIP 2014–2023 Annex B | 9
ENTSOG TYNDP 2013-2013 - Annex A
Made with FlippingBook