ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
TRA-N-128
Compressor Station Kipi
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Public Financing
DESFA S.A.
Project of Common Interest
TEN-E Project ?
–
Operator
Private Financing
DESFA S.A.
Yes
In PCI list ?
–
Multilateral Financing
None
IGAs
–
Web Link
www.desfa.gr
TEN-E Requests
Date of Request
Year Funding Granted
01.04.2005
2013
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Regulated
2014
3
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
2014
Applied for Exemption ?
Construction
Total Compressor Power (MW)
No
2015
+56.10
Exemption granted ?
Commissioning
Expected Load Factor
Not relevant
2019
+0.90
% Exemption in entry direction
Last completed Phase :
Diameter (range) (mm)
–
FEED
% Exemption in exit direction
Diameter (range) (inches)
–
Southern Corridor GRIP 2014–2023 Annex B |
88