PROJECTED CAPACITY INCREASES Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction No exit Yes entry
Rogatec
165.00 165.00
Hub Slovenia
Hub Croatia
DESCRIPTION OF THE PROJECT
Upgrading of the existing interconnection Croatia/Slovenia
EXPECTED BENEFITS
Security of Supply, Market integration (croatian market and the markets in CEE region), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (for Croatia and Slovenia), N-1 Regional, Back-up for renewables, It will significantly increase the capacity of the interconnection of the Croatian and Slovenian gas transmission systems in this direction. It will increase the capacity along the route, providing enhanced access to Baumgarten and to the Italian gas market, for gas supplied through LNG terminals on the Croatian coast or through IAP.
COMMENTS ABOUT THE PROJECT FINANCING Public financing
Private financing
Multilateral financing