ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects

PROJECTED CAPACITY INCREASES Interconnection

Capacity (GWh/d)

From Zone

To Zone

Modelled Direction No exit Yes entry

Rogatec

165.00 165.00

Hub Slovenia

Hub Croatia

DESCRIPTION OF THE PROJECT

Upgrading of the existing interconnection Croatia/Slovenia

EXPECTED BENEFITS

Security of Supply, Market integration (croatian market and the markets in CEE region), Reverse Flows, Diversification of sources, Diversification of routes, N-1 National (for Croatia and Slovenia), N-1 Regional, Back-up for renewables, It will significantly increase the capacity of the interconnection of the Croatian and Slovenian gas transmission systems in this direction. It will increase the capacity along the route, providing enhanced access to Baumgarten and to the Italian gas market, for gas supplied through LNG terminals on the Croatian coast or through IAP.

COMMENTS ABOUT THE PROJECT FINANCING Public financing

Private financing

Multilateral financing

Southern Corridor GRIP 2014–2023 Annex B |