ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
TRA-N-068
Ionian Adriatic Pipeline
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Public Financing
Not part of TEN-E
Sponsors include (in addition to Plinacro) : the Albanian Ministry of Economy, Trade and Energy, the Montenegro Ministry of Economy, the Bosnia & Herzegovina Ministry of Foreign Trade and Economic Relations
TEN-E Project ?
–
Private Financing
Yes
In PCI list ?
–
Multilateral Financing
2
IGAs
–
Promoter
Plinacro Ltd
Web Link
www.plinacro.hr
Operator
Plinacro Ltd
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Regulated
3
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
+540
Applied for Exemption ?
Construction
Total Compressor Power (MW)
No
2015
Exemption granted ?
Commissioning
Expected Load Factor
No
2020
% Exemption in entry direction
Last completed Phase :
Diameter (range) (mm)
–
Planned
DN 800
% Exemption in exit direction
Diameter (range) (inches)
–
32"
Feasibility study to be completed in 2014