ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
*
TRA-N-035
Tauerngasleitung Gas Pipeline Project
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Public Financing
Tauerngasleitung GmbH
Project of common interest
TEN-E Project ?
–
Operator
Private Financing
Tauerngasleitung GmbH
Yes
In PCI list ?
70%
Multilateral Financing
None
IGAs
30%
* On 2.4.2014 the sponsor’s shareholders announced that they intended to amend the sponsor’s ownership structure through a tendering process. The TGL GmbH was liquidated on 11.4.2014
Web Link
www.tauerngasleitung.at
TEN-E Requests
Date of Request
Year Funding Granted
28.04.2010 26.04.2006
2011 2007
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Regulated
2014 Q4
1
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
2014 Q2
+290
Applied for Exemption ?
Construction
Total Compressor Power (MW)
Not yet
2015 Q1
+66.00
Exemption granted ?
Commissioning
Expected Load Factor
No
2018 Q4
% Exemption in entry direction
Last completed Phase :
Diameter (range) (mm)
–
Planned
DN 900
% Exemption in exit direction
Diameter (range) (inches)
–
36"