TRA-N-012
GALSI Pipeline
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Edison SpA
Public Financing
21%
Project of European Interest
TEN-E Project ?
–
SONATRACH
Private Financing
42%
Yes
In PCI list ?
–
Sfirs SpA
Multilateral Financing
12%
1
IGAs
–
Hera Trading Srl
10%
Web Link
www.galsi.it
Enel Produzione SpA
16%
Promoter
Edison
Operator
Galsi S.p.A.
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Regulated
2014 Q1
3
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
2014 Q2
+861
Applied for Exemption ?
Construction
Total Compressor Power (MW)
Not relevant
2015 Q1
+151
Exemption granted ?
Commissioning
Expected Load Factor
Not relevant
2018 Q1
% Exemption in entry direction
Last completed Phase :
Diameter (range) (mm)
–
FEED
DN 650 to 1200
% Exemption in exit direction
Diameter (range) (inches)
–
26" to 48"