ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects

PROJECTED CAPACITY INCREASES

Interconnection

Capacity (GWh/d)

From Zone

To Zone

Modelled Direction Yes entry

New Entry Point in South Italy

264.00

Trans-Adriatic Pipeline (Greece) Hub Italia

DESCRIPTION OF THE PROJECT

Project title changed since TYNDP 2013-2022 publication. The project consists in new on-shore pipeline and compressor station along the center-south of Italy that will allow the increase of transport capacity at new or existing Entry Points in south Italy. The implementation plan and, in particular, the FID could be influenced by other projects creating a new entry point in southern Italy, in the context of the Southern Gas Corridor.

EXPECTED BENEFITS

Security of Supply, Market integration, Diversification of sources, Diversification of routes, N-1 National (Italy), Back-up for renewables, Power-to-gas, Market Integration (Increase of competition), Flexibility of the system.

COMMENTS ABOUT THE PROJECT FINANCING Public financing

Private financing

Multilateral financing