PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone Hub Italia
To Zone
Modelled Direction Yes exit
Griespass (CH) / Passo Gries (IT)
54.00
Hub Switzerland
DESCRIPTION OF THE PROJECT Project title changed since TYNDP 2013-2022 publication. The project consists in new on-shore pipelines in the north of Italy and it permits to increase the flexibility of the gas transmission and the security of supply in the north-west area of Italy, allowing a first step of export capacity.
EXPECTED BENEFITS
Security of Supply, Market integration, Reverse Flows, Diversification of routes, N-1 Regional, Back-up for renewables, Power-to-gas, Market Integration (Increase of competition), Flexibility of the system, reducing of GHG emissions.
COMMENTS ABOUT THE PROJECT FINANCING Public financing
Private financing
Multilateral financing