UGS-N-234

Zsana UGS - Decrease of the minimum injection capacity

Non-FID

Storage Facility

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter

Public Financing

Hungarian Gas Storage Ltd. Hungarian Gas Storage Ltd.

Project of Common Interest

TEN-E Project ?

Operator

Private Financing

No

In PCI list ?

Multilateral Financing

None

IGAs

Web Link

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Considered TPA Regime

End of permitting phase

Storage facility

Regulated

2015 Q3

Zsana

Considered Tariff Regime

FID

Working volume (mcm)

Regulated

2015 Q4

+2,140

Applied for Exemption ?

Construction

Injectability (mcm/d)

No

2016 Q1

+17.20

Exemption granted ?

Commissioning

Deliverability (mcm/d)

No

2017 Q1

+28.00

% Exemption in entry direction

Last completed Phase :

Market test

% Exemption in exit direction