ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
UGS-F-260
System Enhancements - Stogit - on-shore gas fields
FID
Storage Facility
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Public Financing
STOGIT
Not part of TEN-E
TEN-E Project ?
–
Operator
Private Financing
STOGIT
No
In PCI list ?
–
Multilateral Financing
None
IGAs
–
Web Link
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
Storage facility
Regulated
2014 Q2
Stogit Enhancements and New Developments
Considered Tariff Regime
FID
Working volume (mcm)
Regulated
2006 Q2
+2,003.70
Applied for Exemption ?
Construction
Injectability (mcm/d)
No
2012 Q4
Exemption granted ?
Commissioning
Deliverability (mcm/d)
Not relevant
2016 Q4
+22.20
% Exemption in entry direction
Last completed Phase :
–
FID
% Exemption in exit direction
–
Southern Corridor GRIP 2014–2023 Annex B |