UGS-F-259

Bordolano

FID

Storage Facility

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter

Public Financing

STOGIT

Not part of TEN-E

TEN-E Project ?

Operator

Private Financing

STOGIT

No

In PCI list ?

Multilateral Financing

None

IGAs

www.stogit.it/en/activities/Innovation-and- research/Progetto_Bordolano.html

Web Link

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Considered TPA Regime

End of permitting phase

Storage facility

Regulated

2013 Q4

Bordolano

Considered Tariff Regime

FID

Working volume (mcm)

Regulated

2006 Q2

+1,136

Applied for Exemption ?

Construction

Injectability (mcm/d)

No

2013 Q4

+14.20

Exemption granted ?

Commissioning

Deliverability (mcm/d)

Not relevant

2015 Q4

+18.90

% Exemption in entry direction

Last completed Phase :

FID

% Exemption in exit direction