ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects

Print

UGS-F-236

San Potito e Cotignola

FID

Storage Facility

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter

Public Financing

Edison Stoccagio S.p.A.

Not part of TEN-E

TEN-E Project ?

Operator

Private Financing

Edison Stoccagio S.p.A.

No

In PCI list ?

Multilateral Financing

None

IGAs

Web Link

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Considered TPA Regime

End of permitting phase

Storage facility

Regulated

2009 Q2

San Potito e Cotignola

Considered Tariff Regime

FID

Working volume (mcm)

Regulated

2006 Q3

+868

Applied for Exemption ?

Construction

Injectability (mcm/d)

No

2010 Q2

+6.80

Exemption granted ?

Commissioning

Deliverability (mcm/d)

Not relevant

2013 Q2

+6.80

% Exemption in entry direction

Last completed Phase :

Commissioning

% Exemption in exit direction

Southern Corridor GRIP 2014–2023 Annex B |

128

ENTSOG TYNDP 2013-2013 - Annex A

Made with