ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
Plinovodi projects cluster 6
Code
Name
Commissioning
Technical information
FID status
TEN-E
PCI project
M9a Lendava - Kidričevo M10 Vodice - Rateče M9b Kidričevo - Vodice
Pipeline 72 km and Compressor station 80 MW non-FID
2016 2017 2018
TEN-E 2011
No No No
TRA-N-098 TRA-N-100 TRA-N-263
Pipeline 79 km
non-FID
TEN-E 2010, 2011
Pipeline 115 km and Compressor station 60 MW non-FID
TEN-E 2012
GENERAL INFORMATION
Promoter Operator
Plinovodi Plinovodi
THIRD-PARTY ACCESS REGIME
Considered TPA Regime
Negotiated
Considered Tariff Regime
Negotiated
Applied for Exemption ?
Not yet
Web Link
www.plinovodi.si/wp-content/uploads/2011/09/RN-2014-2023.pdf
DESCRIPTION AND BENEFITS OF THE PROJECT
These projects aim at providing additional supply to the Slovenian gas market, but mainly represent a substantial transit capacity to the Slovenian transmission system from Hungary to Italy, establishing two new Interconnection Points: - one at the Slovenian-Hungarian border (Lendava) with an entry capacity of 288 GWh/d, possibly increasing to 819 GWh/d and - one at the Slovenian-Italian border (Tarvisio) with an exit capacity of 819 Gwh/d. The implementation of the project depends on the existence of corresponding upstream (within Hungary) transmission capacity.