ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
PROJECTED CAPACITY INCREASES Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes exit
Posušje
45.00
Ionic-Adriatic Pipeline (Croatia) Hub Bosnia & Herzegovina
DESCRIPTION OF THE PROJECT
South Interconnection of Croatia and Bosnia & Herzegovina. The pipeline will be a branch from the planned regional Ionic Adriatic Pipeline - IAP along the routing: Zagvorzd-Imotski.
EXPECTED BENEFITS
Security of Supply, Market integration, Diversification of sources, N-1 National (for BH), N-1 Regional, The aim of the project is to establish a new supply route for BH providing a diversified and reliable natural gas supply.
COMMENTS ABOUT THE PROJECT FINANCING Public financing
Private financing
Multilateral financing