ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
TRA-N-188
Reverse flow at GR-BG border (Greek part)
FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Public Financing
DESFA S.A.
Not part of TEN-E
TEN-E Project ?
–
Operator
Private Financing
DESFA S.A.
Yes
In PCI list?
100%
Multilateral Financing
None
IGAs
–
Web Link
wwwdesfa.gr
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Regulated
1
Considered Tariff Regime
FID
Total Pipeline Length (km)
Regulated
2013 Q3
Total Compressor Power (MW)
Applied for Exemption ?
Construction
Not relevant
2013 Q3
*
Exemption granted ?
Commissioning
Expected Load Factor
Not relevant
2014 Q2
+0.80
% Exemption in entry direction
Last completed Phase :
Diameter (range) (mm)
–
Construction
* This date refers to the 1st phase of the project.
% Exemption in exit direction
Diameter (range) (inches)
–
Southern Corridor GRIP 2014–2023 Annex B |
100
ENTSOG TYNDP 2013-2013 - Annex A
Made with FlippingBook