ENTSOG Gas Regional Investment Plan South 2017 - Main Report
6.2.3.1.2 Between Spain and France
Following the Madrid Declaration in March 2015, a High Level Group (HLG) for Interconnections in Western Europe was established in order to follow its implemen- tation. As part of the work done in this HLG, a Joint Technical Study between Enagás, GRTgaz and TIGF related to MidCat was developed during summer 2015. Two different approaches were used in this technical study: \\ The minimum infrastructure required for connecting both countries: STEP project. \\ The infrastructures required to achieve the target firm capacity (230GWh/d from Spain to France and 180GWh/d from France to Spain): MidCat project. STEP (TRA-N-161 + TRA-N-252) In Spain, this project (TRA-N-161) consists of two pipelines (Hostalrich – Figueras and Figueras-French border), and a new compressor station in Martorell (36MW). In France (TIGF zone), the project (TRA-N-252) consists in a pipeline between Barbaira and the Spanish border. The total length of the project is 107km in Spain and 120km in France. The commissioning date of this project is 2021 in Spain and 2022 in France (TIGF). This project does not create firm annual capacities in both sides of the interconnec- tion. Consequently, the capacity created by this project is not considered in the TYNDP 2017, as ENTSOG NeMo tool only considers firm capacities on an annual basis. Nevertheless, according to a probabilistic study developed by Enagás, this project creates in the Spanish side firm capacity: 120GWh/d from Spain to France, and 110GWh/d from France to Spain. Such probabilistic analysis wasn’t performed on the French side as the behavior of the French market may change after the merg- er of zones in 2018. According to TYNDP 2017 criteria the project was defined as “Advanced non-FID”, as it received a CEF grant for FEED studies in the second CEF-E call of 2015 5) .
STEP PROJECT: INFRASTRUCTURES
Commission- ing Year
Length (km)
Diameter (mm)
Compressor Power (MW)
Type
TYNDP Code Name
Status
Section
South Transit East Pyrenees (STEP) – Enagás South Transit East Pyrenees (STEP) – Enagás South Transit East Pyrenees (STEP) – Enagás South Transit East Pyrenees (STEP) – TIGF
Pipeline including CS
Advanced Non-FID
TRA-N-161
2021
CS Martorell
36
Pipeline including CS
Advanced Non-FID
Hostalrich – Figueras
TRA-N-161
2021
79
900
Pipeline Figueras – French Border Pipeline Spanish Border- Barbaira
Pipeline including CS
Advanced Non-FID
TRA-N-161
2021
28
900
Pipeline including CS
Advanced Non-FID
TRA-N-252
2022
120
900
Table 6.8: STEP project: infrastructures (Source: TYNDP 2017)
5) Spain: https://ec.europa.eu/inea/sites/inea/files/fiche_5.5-0054-esfr-s-m-15_final.pdf France: https://ec.europa.eu/inea/sites/inea/files/fiche_5.5-0048-fr-s-m-15_final.pdf
Gas Regional Investment Plan of the South Region 2017 | 81