ENTSOG Gas Regional Investment Plan South 2017 - Main Report

6.2.3.1 Projects developing Interconnection capacities within the South Region

CAPACITY CREATED BY TRANSMISSION PROJECTS IN THE SOUTH REGION

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

ES > PT

144 144 144 134 134 134 204 204 204 204 273 273

VIP IBERICO

PT > ES

80

80

80

62

62

62 132 132 132 132 188 188

ES > FR

225 225 225 225 225 225 225 225 225 455 455 455

VIP PIRINEOS

FR > ES

165 165 165 165 165 165 165 165 165 325 325 325

Less advanced non-FID

Table 6.6: Capacity created by transmission projects in the South Region (Source: TYNDP 2017)

Image courtesy of REN

78 |

Gas Regional Investment Plan of the South Region 2017