In 2018, three FID projects will be commissioned, all located in France. Most Non-FID advanced projects and Non-FID less-advanced projects are planned to be commissioned between 2020 and 2022.

Commissioning year

8

7

6 5 4 3 2 1

0

2018

2019

2020

2021

2022

2023

2024

2025

2026

Unknown

LNG Terminal – FID Transmission – FID

LNG Terminal – Less-Advanced Non-FID Transmission – Advanced Non-FID

Transmission – Less-Advanced Non-FID

Storage Facility – Less-Advanced Non-FID

Figure 6.5: Commissioning year of South Region projects (Source: TSO own elaboration)