5.4 IP Subscription and Use

5.4.1 CAPACITY SUBSCRIPTION AT NORTH-SOUTH LINK (FRANCE) Since April 2014, firm capacity has been set to 270GWh/d, to which up to 150GWh/d of interruptible capacity can be booked. GRTgaz also offers additional service to maximise the access to TRS with the JTS (Joint Transport Storage service) and mar- ket coupling mechanism. Annual capacities are sold through auctions once a year, annual interruptible capacity is available only if 95% of firm capacities has been sold. Since the North South link will disappear in November 2018, last auction for annual available capacity will occur in March 2018. Use of the North-South link is still very high, with a 95% use of available technical capacity in 2016. Firm capacity in the opposite direction is booked at 26%.

GWh/d

North-South Link (North – South direction)

500 400 350 300 250 200 150 100 50 450

0

Jan 14

Jul 14

Jan 15

Jul 15 Jan 16

Jul 16

Jan 17

Jul 17

Jan 18 Jul 18

Booked Firm Capacity North-South Booked Interruptible Capacity North-South Firm Capacity North-South Allocation

Interruptible Capacity North-South Available Interruptible Capacity North-South Available Firm Capacity North-South

Figure 5.12: Capacity subscription at North-South Link (France), North-South direction (Source: TSO own elaboration)

GWh/d

North-South Link (South – North direction)

600

500

400

300

200

100

0

Jan 14

Jul 14

Jan 15

Jul 15 Jan 16

Jul 16

Jan 17

Jul 17

Jan 18 Jul 18

Booked Firm Capacity South-North Booked Interruptible Capacity South-North Firm Capacity South-North Allocation

Interruptible Capacity South-North Available Interruptible Capacity South-North Available Firm Capacity South-North

Figure 5.13: Capacity subscription at North-South Link (France), South-North direction (Source: TSO own elaboration)

60 |

Gas Regional Investment Plan of the South Region 2017