ENTSOG Gas Regional Investment Plan (GRIP) 2017 - 2026 / Southern Corridor / Main Report
2.3 Projects involving more than two EU Countries or non EU Countries or Offshore Projects
PROJECTS INVOLVING MORE THAN TWO EU COUNTRIES OR NON EU COUNTRIES OR OFFSHORE PROJECTS
Commissioning (TYNDP 2017)
PCI 2015 Code Promoter
Status
Project
TYNDP Code
Interconnection Bulgaria – Serbia TRA-F-137
6.10
Ministry of Energy of Bulgaria
FID
2018*
TANAP – Trans Anatolian Natural Gas Pipeline Project
TRA-F-221
7.11
FID
2018
Trans Adriatic Pipeline
TRA-F-051
7.1.3
FID
2019
Advanced Non-FID
Poseidon Pipeline
TRA-N-010
7.1.4
2020
EastMed Pipeline
TRA-N-330
7.3.1
Non-FID 2020
White Stream
TRA-N-053
–
Non-FID 2022
W-Stream
Interconnection Bulgaria – FYRoM TRA-N-976
–
MER JSC Skopje
Non-FID 2021
Interconnection Greece – FYRoM (FYRoM part)
TRA-N-980
–
MER JSC Skopje
Non-FID 2021
* Since the submission of project data for the preparation of the TYNDP 2017, the commissioning date has been moved to 2020
32 |
Southern Corridor GRIP 2017–2026